EPA Construction General Permit (Stormwater)
Stormwater/erosion permit required when a job disturbs one acre or more. In New Mexico apply to EPA (not NMED).
Who needs it
Any project disturbing 1+ acre, or a smaller part of a larger common plan totaling 1+ acre.
Steps to get it
- 1 Determine if the job disturbs 1+ acre (or is part of a larger 1+ acre plan).
- 2 Develop a Stormwater Pollution Prevention Plan (SWPPP) with erosion/sediment controls.
- 3 File a Notice of Intent (NOI) through EPA NeT system before disturbing ground.
- 4 File a Notice of Termination (NOT) once the site is stabilized.
Authority & citation
Clean Water Act Sec. 402; NPDES (40 CFR 122). New Mexico is a non-delegated state, so EPA is the permitting authority.